# Project Lightning — Kingfish > Kingfish's investigation into the Applied Digital "Delta Forge 1" data center in central Louisiana — its permits, power demand, and public subsidies. Status: ongoing. License: CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Attribution: Kingfish Media. ## Key facts - **Facility:** Delta Forge 1 data center - **Operator:** Applied Digital Corporation - **Regulator:** Louisiana DEQ - **Estimated interconnection cost:** $4.2 million ## Timeline - 2024-02-01: Kingfish files DEQ records request DEQ-2024-042. - 2024-03-15: Applied Digital files an air-permit variance application. - 2024-05-28: DEQ fulfills the records request. ## Entities - Applied Digital Corporation — Organization (https://opencorporates.com/companies/us_nv/applied-digital, https://www.wikidata.org/wiki/Q123456789) - Louisiana Department of Environmental Quality — GovernmentAgency (https://www.deq.louisiana.gov/) - Delta Forge 1 — Place --- # Delta Forge 1: What the first permit filings show > The records behind Applied Digital's central Louisiana data center. **By:** kingfish-staff **Published:** 2026-06-03 **Canonical:** https://kingfish.la/delta-forge-first-permit **License:** CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/) **Cite as:** kingfish-staff (2026). Delta Forge 1: What the first permit filings show. Kingfish. https://kingfish.la/delta-forge-first-permit **Investigation:** Project Lightning — Kingfish's investigation into the Applied Digital "Delta Forge 1" data center in central Louisiana — its permits, power demand, and public subsidies. --- Applied Digital's Delta Forge 1 data center first surfaced in state records in the spring of 2024. The company's own filings tell the story. In its application to the state, [the company sought relief from baseline emissions limits](/docs/deq-2024-042-001#page=4) for the facility — a request that would let Delta Forge 1 run its generators beyond the standard cap. Utility correspondence obtained through the same request shows [the interconnection was estimated at $4.2 million](/docs/deq-2024-042-002#page=2), a cost that lands on the grid before a single server is switched on. Both documents came from a single Louisiana DEQ records request, fulfilled in May 2024. --- ## Sources - [Air permit variance application — Delta Forge 1](https://kingfish.la/docs/deq-2024-042-001) — Louisiana DEQ, request DEQ-2024-042 (p.4) - [Interconnection cost estimate — Delta Forge 1](https://kingfish.la/docs/deq-2024-042-002) — Louisiana DEQ, request DEQ-2024-042 (p.2) --- ## Citation formats ### BibTeX ```bibtex @misc{kingfish-delta-forge-first-permit, author = {kingfish-staff}, title = {Delta Forge 1: What the first permit filings show}, year = {2026}, publisher = {Kingfish Media}, howpublished = {\url{https://kingfish.la/delta-forge-first-permit}}, note = {Accessed: June 5, 2026. License: CC BY 4.0} } ``` ### CSL-JSON ```json [ { "id": "kingfish-delta-forge-first-permit", "type": "article", "title": "Delta Forge 1: What the first permit filings show", "author": [ { "literal": "kingfish-staff" } ], "issued": { "date-parts": [ [ 2026 ] ] }, "publisher": "Kingfish Media", "URL": "https://kingfish.la/delta-forge-first-permit", "license": "https://creativecommons.org/licenses/by/4.0/" } ] ```