# Eight Alexandria budgets listed a $900,000 water-tank repair. None paid for it.

> In October the state found an opening in the top of the Industrial Park water tank. Every capital budget since 2019-20 has listed its $900,000 repair and scheduled the money after the plan ends.

**By:** Bentley Hensel  
**Published:** 2026-11-19  
**Updated:** 2026-11-20  
**Canonical:** https://kingfish.la/industrial-park-tank-deferred/  
**License:** CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/)  
**Cite as:** Bentley Hensel (2026). Eight Alexandria budgets listed a $900,000 water-tank repair. None paid for it.. Kingfish. https://kingfish.la/industrial-park-tank-deferred/

---

On Oct. 8, 2026, the Louisiana Department of Health told Mayor Jacques Roy that a drone inspection had found "a damaged sensor on the top of the tank which provided a direct pathway for contamination to enter the finished water storage tank." The [notice](https://media.kingfish.la/2026/11/docs/32CBEAA7-A110-C17F-87B0-A188E1500000.pdf?ref=kingfish.la#page=2) concerns the city's elevated water tank at the Industrial Park. The city's operator took the tank out of service immediately, it says.

Every Alexandria capital budget since 2019-20 has listed "Industrial Park Tank Repair & Paint" at $900,000, and seven of them rate it Priority A. Four of those budgets were Jeff Hall's and four are Roy's. None scheduled the money inside its own five-year plan.

LDH gave the city 30 days from receiving the letter to fix the opening and answer in writing. The city submitted information to clear the violation on Nov. 5, LDH said in response to questions from The Kingfish Project.

![LDH drone photo of the damaged sensor on top of the Industrial Park elevated tank](https://media.kingfish.la/2026/11/industrial-tank.png)

Damaged Sensor on Elevated Tank @ Industrial Park

## The short version

-   **The notice.** LDH's [Oct. 8 notice of violations](https://media.kingfish.la/2026/11/docs/32CBEAA7-A110-C17F-87B0-A188E1500000.pdf?ref=kingfish.la#page=1) cites the city under the state rule that finished-water tanks be **"tightly covered and of watertight construction."** The city had **30 days** to fix the opening and report back.
-   **No contamination reported.** Neither of LDH's citations is a test result, and no contamination of water delivered to customers is reported.
-   **Cleared Nov. 5.** The city submitted information to clear the violation on Nov. 5, LDH said.
-   **Eight budgets, one entry.** The repair appears in every capital budget from [2019-20](https://media.kingfish.la/2026/11/docs/2019-20_Capital_Budget.pdf?ref=kingfish.la#page=190) through [2026-27](https://media.kingfish.la/2026/11/docs/2026-27_Capital_Budget.pdf?ref=kingfish.la#page=192) at **$900,000, rated Priority A in seven of them**. The money was scheduled **"Beyond 2024"** in the first and **"Beyond 2031"** in the latest.
-   **No contract.** A review of more than 40 council packets from August 2024 to November 2026 found no bid, contract, or engineering item for the repair.
-   **A second tank, two years earlier.** In October 2024, LDH [found two holes in the top of the city's Willow Glen River Road tank](https://media.kingfish.la/2026/11/docs/AA065928-FE54-CADB-86EF-928C02000000.pdf?ref=kingfish.la#page=1) and cited the same rule. LDH says the holes were closed Oct. 18, 2024.
-   **The election.** Roy faces City Council member Malcolm Larvadain in the Dec. 12 runoff.

## What the rule requires

Water in an elevated tank has already been treated and is on its way to customers' taps. The state sanitary code requires every such tank to be "tightly covered and of watertight construction" ([LAC 51:XII §337.A](https://ldh.la.gov/assets/oph/Center-EH/drinkingwater/Watergrade/Part-XII.pdf?ref=kingfish.la)). LDH cited the city under that section and under the rule that tank vents and overflows must keep out "birds, insects, dust or other contaminating material" ([notice, p.1](https://media.kingfish.la/2026/11/docs/32CBEAA7-A110-C17F-87B0-A188E1500000.pdf?ref=kingfish.la#page=1)). Both are construction rules.

Under the federal Ground Water Rule ([40 CFR § 141.404](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-D/part-141/subpart-S/section-141.404?ref=kingfish.la)), LDH treats a defect like this as a "significant deficiency," a problem the water system must correct. The tank cannot return to service until a bacteria test comes back negative for total coliform and the water carries at least 0.5 milligrams per liter of chlorine.

## Eight budgets, one entry

Each project sheet gives the same reason for the repair: "Tank interior and exterior walls are in need of repair and painting." The sheet describes the walls. LDH's October finding was a damaged sensor on top of the tank, and the budgets do not say whether the $900,000 project would have covered it.

Every entry carries the same $900,000 from the utility fund, with nothing carried over from an earlier year. Seven budgets include a project sheet rating it Priority A. The 2025-26 budget lists it only in the water department's five-year plan table, which gives no priority. Hall's first capital budget, for 2019-20, added the project.

## Where the money sits

None of the eight budgets put the repair money inside its five-year plan. Each listed it in the column after the plan's final year, and each new budget moved that column forward one year, from "Beyond 2024" in [2019-20](https://media.kingfish.la/2026/11/docs/2019-20_Capital_Budget.pdf?ref=kingfish.la#page=190) to "Beyond 2031" in [2026-27](https://media.kingfish.la/2026/11/docs/2026-27_Capital_Budget.pdf?ref=kingfish.la#page=192). A project listed this way keeps its place on the list without ever reaching a year in which it is funded. A review of more than 40 council packets from August 2024 to November 2026 found no bid, contract or engineering item for the repair.

## The record since 2016

LDH inspects the system in periodic sanitary surveys, and [EPA's records](https://echo.epa.gov/detailed-facility-report?fid=LA1079001&sys=SDWIS&ref=kingfish.la) log what those surveys find.

Year

What LDH found

Source

2016

Significant deficiencies in finished-water storage

[EPA](https://echo.epa.gov/detailed-facility-report?fid=LA1079001&sys=SDWIS&ref=kingfish.la)

2018

Tank-vent deficiency

[EPA](https://echo.epa.gov/detailed-facility-report?fid=LA1079001&sys=SDWIS&ref=kingfish.la)

2020

Significant storage deficiencies; tank-vent deficiency

[EPA](https://echo.epa.gov/detailed-facility-report?fid=LA1079001&sys=SDWIS&ref=kingfish.la)

Oct. 18, 2022

Significant storage deficiencies; citywide boil advisory the same day

[EPA](https://echo.epa.gov/detailed-facility-report?fid=LA1079001&sys=SDWIS&ref=kingfish.la); [KALB](https://www.kalb.com/2022/10/19/city-alexandria-under-system-wide-boil-advisory-includes-woodworth/?ref=kingfish.la#page=171)

Oct. 2, 2024

Two holes in the top of the Willow Glen River Road tank and a broken level-indicator pipe; tank-vent deficiency in EPA's records for that year

[LDH notice](https://media.kingfish.la/2026/11/docs/AA065928-FE54-CADB-86EF-928C02000000.pdf?ref=kingfish.la#page=1); [EPA](https://echo.epa.gov/detailed-facility-report?fid=LA1079001&sys=SDWIS&ref=kingfish.la)

Oct. 8, 2026

Damaged sensor on top of the Industrial Park tank

[LDH notice](https://media.kingfish.la/2026/11/docs/32CBEAA7-A110-C17F-87B0-A188E1500000.pdf?ref=kingfish.la#page=1)

**2022.** EPA's records do not say which tanks the 2016 to 2022 findings involved. On the day of the Oct. 18 survey, during Hall's administration, the city put its entire system, including Woodworth, under a boil advisory "while we complete maintenance at the top of some of our elevated storage tanks," [KALB reported](https://www.kalb.com/2022/10/19/city-alexandria-under-system-wide-boil-advisory-includes-woodworth/?ref=kingfish.la), quoting the city. The city said its water tests had been fine, and it lifted the advisory after repairs and clear state tests. LDH says the city corrected that survey's significant deficiencies on time.

**2024.** LDH inspected the Willow Glen River Road tank by drone on Oct. 2, 2024, and found "2 holes in the top of the tank that provided for a direct pathway for contamination" ([LDH notice, p.1](https://media.kingfish.la/2026/11/docs/AA065928-FE54-CADB-86EF-928C02000000.pdf?ref=kingfish.la#page=1)). LDH's attached drone photo of the tank roof is captioned "Level indicator pipe broken" ([notice, p.3](https://media.kingfish.la/2026/11/docs/AA065928-FE54-CADB-86EF-928C02000000.pdf?ref=kingfish.la#page=3)). Operators isolated the tank and arranged bacteria sampling. LDH cited §337.A, the same section it cited this October, and gave the city 90 days to cap or plug the holes, take a sample confirming the water's sanitary quality before returning the tank to service, and report in writing. LDH would then inspect within five days of the repair or of the 90-day deadline. LDH says the holes were closed on Oct. 18, 2024, and that the city corrected that survey's significant deficiencies on time. EPA's records show no federal violation after it. The letter's first page is dated Oct. 14, 2024, and its later pages are dated Oct. 9.

**The record since 2016:** storage deficiencies in LDH's 2016, 2020, and 2022 surveys; a tank-vent deficiency in four survey years; a citywide boil advisory; and two notices under §337.A in two years, both addressed to Roy.

## Where tank money went

The water department's five-year plans show where tank money went. "Adams Tank Repair & Paint" carried $1.85 million into 2023-24 and $1.04 million into 2025-26 ([2023-24, p.153](https://media.kingfish.la/2026/11/docs/2023-24_Capital_Budget.pdf?ref=kingfish.la#page=153); [2025-26, p.232](https://media.kingfish.la/2026/11/docs/2025-26_Capital_Budget.pdf?ref=kingfish.la#page=232)). LDH certified a new aeration system at the Kisatchie ground storage tank as complete on Feb. 3, 2025 ([LDH certificate, p.2](https://media.kingfish.la/2026/11/docs/74CB4C6E-0F48-CF30-9334-9A7897400000.pdf?ref=kingfish.la#page=2)). In September the council voted 7-0 to seek bids for a Highway 1 South booster station, ground storage tank and water main ([Oct. 6, 2026 packet, p.10](https://media.kingfish.la/2026/11/docs/October-06-2026-Council-Info-Packet.pdf?ref=kingfish.la#page=10); [Nov. 3 packet, p.2](https://media.kingfish.la/2026/11/docs/November-03-2026-Council-Meeting-Info-packet.pdf?ref=kingfish.la#page=2)). Industrial Park stayed unfunded through all of it. By 2025-26, "Hamilton Tank Painting" and "Shell Road Tank Painting" had joined it on the unfunded list at $900,000 each.

## What we don't know yet

-   **What the city told LDH on Nov. 5,** and whether the Industrial Park tank is back in service.
-   **Which tanks the 2016 to 2022 deficiencies involved.** EPA's records give the deficiency, not the tank.
-   **Why the repair never moved into a funded year.** The eight budgets carry the project without explaining its schedule.

LDH answered our questions on Nov. 18. We have also asked the City of Alexandria, and we will update this piece as answers come in.

#### ✅️ LDH responses to our questions

1.  Did the city repair the Industrial Park tank within 30 days of the Oct. 8, 2026 notice, and has it answered in writing?  
    ****Answer:**** Yes, they submitted information to clear it on November 5.  
    
2.  Were the two holes in the Willow Glen tank found in October 2024 closed, and when?  
    ****Answer:**** Yes, on October 18, 2024.  
    
3.  Did the city correct the significant deficiencies found in the Oct. 18, 2022 and Oct. 2, 2024 sanitary surveys?  
    ****Answer:**** Yes, all on time.

⛔

LDH answered our questions on Nov. 18. The city did not respond by our deadline. We will update this piece if it does.

## How to check this yourself

1.  **Read the notices.** The [Oct. 8, 2026 notice](https://media.kingfish.la/2026/11/docs/32CBEAA7-A110-C17F-87B0-A188E1500000.pdf?ref=kingfish.la#page=1) covers the Industrial Park tank and the [October 2024 notice](https://media.kingfish.la/2026/11/docs/AA065928-FE54-CADB-86EF-928C02000000.pdf?ref=kingfish.la#page=1) covers Willow Glen. Both are short.
2.  **Open the capital budgets.** Each page link in the table above opens on the page that carries the repair. Search any year's budget for "Industrial Park Tank."
3.  **Look up the system.** EPA's [facility report](https://echo.epa.gov/detailed-facility-report?fid=LA1079001&sys=SDWIS&ref=kingfish.la) for public water system LA1079001 lists site visits and deficiencies.
4.  **Read the rules.** [Part XII of the state sanitary code](https://ldh.la.gov/assets/oph/Center-EH/drinkingwater/Watergrade/Part-XII.pdf?ref=kingfish.la) holds §337; the federal corrective-action rule is [40 CFR § 141.404](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-D/part-141/subpart-S/section-141.404?ref=kingfish.la).
5.  **Read the council packets.** The city posts them as PDFs, like the [Oct. 6](https://www.cityofalexandriala.com/wp-content/uploads/2026/09/October-06-2026-Council-Info-Packet.pdf?ref=kingfish.la#page=10) and [Nov. 3](https://www.cityofalexandriala.com/wp-content/uploads/2026/10/November-03-2026-Council-Meeting-Info-packet.pdf?ref=kingfish.la#page=2) packets cited here. Agendas and minutes are also at [meetings.kingfish.la](https://meetings.kingfish.la/?ref=kingfish.la).

* * *

The project has sat on the list for eight years at $900,000, its money always one year past the end of the plan. In October the state found an opening in the top of the tank, the city's second notice under the same rule in two years.

_Spot an error? Receipts welcome: tips@kingfish.la._

### Sources

-   City of Alexandria, Annual Capital Budget and Five Year Plan: [2019-20, p.190](https://media.kingfish.la/2026/11/docs/2019-20_Capital_Budget.pdf?ref=kingfish.la#page=190) (printed p.176) · [2020-21, p.176](https://media.kingfish.la/2026/11/docs/2020-21_Capital_Budget.pdf?ref=kingfish.la#page=176) · [2021-22, p.165](https://media.kingfish.la/2026/11/docs/2021-22_Capital_Budget.pdf?ref=kingfish.la#page=165) · [2022-23, p.187](https://media.kingfish.la/2026/11/docs/2022-23_Capital_Budget.pdf?ref=kingfish.la#page=187) · [2023-24, p.153](https://media.kingfish.la/2026/11/docs/2023-24_Capital_Budget.pdf?ref=kingfish.la#page=153) and [p.171](https://media.kingfish.la/2026/11/docs/2023-24_Capital_Budget.pdf?ref=kingfish.la#page=171) · [2024-25, p.198](https://media.kingfish.la/2026/11/docs/2024-25_Capital_Budget.pdf?ref=kingfish.la#page=198) · [2025-26, p.232](https://media.kingfish.la/2026/11/docs/2025-26_Capital_Budget.pdf?ref=kingfish.la#page=232) · [2026-27, p.192](https://media.kingfish.la/2026/11/docs/2026-27_Capital_Budget.pdf?ref=kingfish.la#page=192)
-   Louisiana Department of Health, Office of Public Health: [Notice of Violations, Industrial Park tank, Oct. 8, 2026](https://media.kingfish.la/2026/11/docs/32CBEAA7-A110-C17F-87B0-A188E1500000.pdf?ref=kingfish.la#page=1) (LDH document 32CBEAA7) · [Notice of Violation, Willow Glen River Road tank, Oct. 14, 2024](https://media.kingfish.la/2026/11/docs/AA065928-FE54-CADB-86EF-928C02000000.pdf?ref=kingfish.la#page=1) (LDH document AA065928) · [Certification of Construction, Kisatchie ground storage aeration, Feb. 3, 2025](https://media.kingfish.la/2026/11/docs/74CB4C6E-0F48-CF30-9334-9A7897400000.pdf?ref=kingfish.la#page=2) (LDH document 74CB4C6E) · Responses to questions from The Kingfish Project, Nov. 18, 2026
-   U.S. EPA: [Safe Drinking Water Information System record for the Alexandria water system (LA1079001)](https://echo.epa.gov/detailed-facility-report?fid=LA1079001&sys=SDWIS&ref=kingfish.la), site visits and deficiencies
-   KALB: ["Alexandria city-wide boil advisory LIFTED," Oct. 19, 2022, updated Oct. 21, 2022](https://www.kalb.com/2022/10/19/city-alexandria-under-system-wide-boil-advisory-includes-woodworth/?ref=kingfish.la). _The city's quoted statement comes from KALB's report._
-   Alexandria City Council packets: [Oct. 6, 2026, p.10](https://media.kingfish.la/2026/11/docs/October-06-2026-Council-Info-Packet.pdf?ref=kingfish.la#page=10) (Resolution 0114-2026, Sept. 22 minutes) · [Nov. 3, 2026, p.2](https://media.kingfish.la/2026/11/docs/November-03-2026-Council-Meeting-Info-packet.pdf?ref=kingfish.la#page=2) (agenda)
-   Rules: [LAC 51:XII, Louisiana sanitary code, water supplies](https://ldh.la.gov/assets/oph/Center-EH/drinkingwater/Watergrade/Part-XII.pdf?ref=kingfish.la) (§337, storage) · [40 CFR § 141.404](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-D/part-141/subpart-S/section-141.404?ref=kingfish.la) (Ground Water Rule, corrective action for significant deficiencies)

---

## Citation formats

### BibTeX

```bibtex
@misc{kingfish-industrial-park-tank-deferred,
  author = {Bentley Hensel},
  title = {Eight Alexandria budgets listed a $900,000 water-tank repair. None paid for it.},
  year = {2026},
  publisher = {The Kingfish Project},
  howpublished = {\url{https://kingfish.la/industrial-park-tank-deferred/}},
  note = {Accessed: November 26, 2026. License: CC BY 4.0}
}
```

### CSL-JSON

```json
[
  {
    "id": "kingfish-industrial-park-tank-deferred",
    "type": "article",
    "title": "Eight Alexandria budgets listed a $900,000 water-tank repair. None paid for it.",
    "author": [
      {
        "literal": "Bentley Hensel"
      }
    ],
    "issued": {
      "date-parts": [
        [
          2026
        ]
      ]
    },
    "publisher": "The Kingfish Project",
    "URL": "https://kingfish.la/industrial-park-tank-deferred/",
    "license": "https://creativecommons.org/licenses/by/4.0/"
  }
]
```